JSW ENERGY (RATNAGIRI) LIMITED, PHASE-I
� Project Size: 1200 MW
� Plant configuration: 4 X 300 MW.
� Project Zero Date: 4th July 07.
� Financial closure: 2nd Aug 07.
� Project Cost: 4500 Cr (Debt: Equity � 75:25).
� Fuel: Imported coal.
� Coal Requirement: 4.14 million Tons /annum.
� Condenser water requirement: 38000 m3 /hr for one unit.
� Raw water requirement: 5842 m3 /day.
� Switchyard: 400 KV GIS.
� Power evacuation: four 400 KV lines to Koyna & Karad (two each)
� Chimneys: Two numbers of 220 meter tall twin-flue chimneys
�
� Scheduled completion of project: 38 months
� Status of project clearances
All clearances for the project have been achieved. Major clearances are:
� NOC from
� Consent from Ministry of
Environment & Forest, Govt. of
� Clearance from Maharashtra Maritime Board for seawater intake & outfall (23rd Apr ������2008)
� CRZ clearance from Ministry of Environment & Forest, Govt. of India (15 Nov 2007)
� Clearance for construction of 220 m Chimneys from Airport Authority of India. (28th March 07)
� Clearance from Factory Inspectorate. (5th March 2008)
� Clearance from Labour Commissioner. (2nd March 2007)
� Clearance for grid connectivity from MSETCL. (20th March 2007)
� Status of Order Placements
All the major orders for the project have been placed.
� BTG
package
: SEC,
� General civil
works : SEW,
� General structural works : Sunil
Hi-tech Ltd,
� Chimneys : Gammon India Ltd, Mumbai.
� Cooling Towers : Paharpur Cooling Towers Ltd, Kolkata.
� Balance of Plant : EDAC-ABB-SEW consortium (EDAC as lead partner).
� Status of Power Plant Activities
|
Main Plant works |
Unit-1 |
Unit-2 |
Unit-3 |
Unit-4 |
|
TG foundation Civil work |
Deck completed |
Deck completed |
TG mat completed |
TG mat completed |
|
TG erection |
TG & condenser erection in progress |
|
|
|
|
Structural Fabrication(Quantity revised) |
99% completed |
91% completed |
68% completed |
49% completed |
|
Structural Erection (Quantity revised) |
79% completed |
71% completed |
37% completed |
21% completed |
|
Boiler |
Pressure part erection � 95%. |
Pressure part erection � 60%. |
Structural erection -75%, |
Structural erection -35%, |
|
ESP |
Erection achieved-47% |
Erection achieved-31% |
Erection started. |
Foundation work in progress |
� BOP Work Progress.
� Chimney-1 (Unit 1 & 2): Outer shell construction completed (214 m).
� Chimney-2 (Unit 3 & 4): Outer shell construction completed (214 m).
� Cooling Tower-1: Basin Hydro test completed.
� Cooling Tower-2: Basin Hydro test completed.
� Cooling Tower-3: Basin civil works completed.
� Cooling Tower-4: 80% basin civil works completed.
� CW Pump House-1 (Unit 1 & 2): 97% civil work completed.
� CW Pump House-2 (Unit 3 & 4): 13.7 % civil work completed.
� GIS building- 64% civil work completed.
� CW & MU piping- CW pipes (unit 1 & 2) fabrication completed.
� MIDC water- 53% Pipe laying completed.
� Power Evacuation
A Joint venture has
been formed with MSETCL for construction of power transmission line. L&T
bagged the contract for execution of transmission line for both New Koyna and
Karad. LOI has been issued to L&T on 2nd July-08. New Koyna line
will be ready by June 09 and karad line will be ready by Dec 2009.��� L&T has mobilized to site and 112 Km
(out of 112 km) check survey for package A (Karad Line) and 57 Km (out of 57
km) check survey for Package B (New Koyna Line) has been completed. Foundations
of 63 nos. locations (out of 322) for package A & 50 nos. locations (out of
160) for package B have been completed. Tower erection of 25 nos. locations
(out of 322) for package A and 07 nos. locations (out of 160) has been
completed.
� Site Address :
JSW Energy (Ratnagiri) Ltd.
At.Nandiwade, Post Jaigad,
Tal. Dist. Ratnagiri. 415614
Phone (02357) 242501-05
Fax - (02357) 242508
� Ratnagiri Office Address:
JSW Energy (Ratnagiri) Ltd.
2nd Floor,
Desai Niwas, Juna Mal Naka,
Ratnagiri. 415612
Phone (02352) 271617
Fax - (02352) 271620